# Test Packets User Guide
|
||||
|
||||
## What are Test Packets?
|
||||
|
||||
Test Packets organize your inspection and testing activities into manageable groups. Think of them as folders that contain all the welds, inspections, and documentation for a specific area or system of your project.
|
||||
|
||||
## Getting Started
|
||||
|
||||
To access Test Packets:
|
||||
1. Login to the system
|
||||
2. Click on **Test Packets** in the main menu
|
||||
3. View existing packets or create new ones
|
||||
|
||||
## Understanding Test Packets
|
||||
|
||||
### What's in a Test Packet?
|
||||
Each packet typically contains:
|
||||
- **Welded joints** ready for inspection
|
||||
- **NDT requirements** (RT, UT, PT, MT, etc.)
|
||||
- **Pressure test information**
|
||||
- **Documentation requirements**
|
||||
- **Sign-off tracking**
|
||||
|
||||
### Packet Organization
|
||||
Packets are usually organized by:
|
||||
- **System numbers** (cooling water, steam, etc.)
|
||||
- **Work areas** (Unit 1, Battery A, etc.)
|
||||
- **Construction phases** (Phase 1, Phase 2, etc.)
|
||||
- **Test pressure levels** (same pressure = same packet)
|
||||
|
||||
## Creating a New Test Packet
|
||||
|
||||
### Basic Setup
|
||||
1. Click **"Create New Packet"**
|
||||
2. Fill in essential information:
|
||||
- **Packet Number**: Unique identifier (often auto-generated)
|
||||
- **System/Area**: Which part of the plant
|
||||
- **Test Pressure**: Required test pressure
|
||||
- **Target Date**: When testing should be completed
|
||||
|
||||
### Adding Welds to Packet
|
||||
**Manual Addition:**
|
||||
1. Click **"Add Welds"** in the packet
|
||||
2. Search for welds by:
|
||||
- ISO number
|
||||
- Line number
|
||||
- Joint number
|
||||
- Date range
|
||||
3. Select welds and click **"Add to Packet"**
|
||||
|
||||
**Bulk Addition:**
|
||||
1. Use **"Import from Weldmap"** feature
|
||||
2. Set criteria (area, date range, etc.)
|
||||
3. System automatically adds matching welds
|
||||
4. Review and confirm selections
|
||||
|
||||
## Managing Packet Contents
|
||||
|
||||
### Viewing Packet Details
|
||||
- **Weld List**: All joints included in packet
|
||||
- **NDT Summary**: Required inspections by type
|
||||
- **Progress Tracking**: Completed vs remaining work
|
||||
- **Status Overview**: Overall packet completion
|
||||
|
||||
### NDT Planning
|
||||
The system automatically calculates:
|
||||
- **RT Requirements**: Based on code requirements
|
||||
- **UT Needs**: Ultrasonic testing assignments
|
||||
- **Surface Testing**: PT/MT requirements
|
||||
- **PMI Checks**: Material verification needs
|
||||
|
||||
### Progress Tracking
|
||||
Monitor completion by:
|
||||
- **Individual weld status** (complete/pending)
|
||||
- **NDT type completion** (RT 85%, UT 60%, etc.)
|
||||
- **Overall packet progress** (ready for pressure test?)
|
||||
- **Documentation status** (certificates received?)
|
||||
|
||||
## NDT Coordination
|
||||
|
||||
### Requesting Inspections
|
||||
1. **Select NDT type** needed (RT, UT, PT, MT)
|
||||
2. **Choose inspection company** from approved list
|
||||
3. **Set priority level** (normal, urgent, hold)
|
||||
4. **Add special instructions** if needed
|
||||
5. **Submit request** to NDT coordinator
|
||||
|
||||
### Tracking NDT Results
|
||||
When results come back:
|
||||
1. **Update test results** in the system
|
||||
2. **Upload reports** (PDF format)
|
||||
3. **Mark accept/reject** status
|
||||
4. **Add repair recommendations** if needed
|
||||
|
||||
### Managing Repairs
|
||||
For rejected welds:
|
||||
1. **Create repair work order**
|
||||
2. **Assign to welding crew**
|
||||
3. **Track repair completion**
|
||||
4. **Schedule re-inspection**
|
||||
5. **Update packet status**
|
||||
|
||||
## Pressure Testing
|
||||
|
||||
### Pre-Test Requirements
|
||||
Before pressure testing, verify:
|
||||
- ✅ All welds completed and accepted
|
||||
- ✅ NDT requirements satisfied
|
||||
- ✅ Temporary supports installed
|
||||
- ✅ Safety permits obtained
|
||||
- ✅ Test equipment ready
|
||||
|
||||
### Test Execution
|
||||
1. **Create test record** in the packet
|
||||
2. **Record test pressure** and duration
|
||||
3. **Document any leaks** or issues found
|
||||
4. **Update test status** (pass/fail)
|
||||
5. **Upload test certificates**
|
||||
|
||||
### Post-Test Activities
|
||||
After successful test:
|
||||
- **Remove temporary supports**
|
||||
- **Update packet to "Tested" status
|
||||
- **Prepare handover documentation**
|
||||
- **Schedule final inspections**
|
||||
|
||||
## Documentation Management
|
||||
|
||||
### Required Documents
|
||||
Each packet needs:
|
||||
- **Weld maps** with joint locations
|
||||
- **NDT reports** for all inspections
|
||||
- **Material certificates** for all components
|
||||
- **Pressure test certificates**
|
||||
- **As-built drawings** if changes made
|
||||
|
||||
### Document Upload
|
||||
1. **Click "Documents" tab** in packet
|
||||
2. **Select document type** from dropdown
|
||||
3. **Upload files** (PDF preferred)
|
||||
4. **Add descriptions** and dates
|
||||
5. **Mark as approved** when reviewed
|
||||
|
||||
### Document Review
|
||||
Track document status:
|
||||
- **Submitted**: Uploaded but not reviewed
|
||||
- **Under Review**: Being checked by QC
|
||||
- **Approved**: Accepted for handover
|
||||
- **Rejected**: Needs corrections
|
||||
|
||||
## Handover Process
|
||||
|
||||
### Preparing for Handover
|
||||
1. **Complete all testing** requirements
|
||||
2. **Gather all documentation**
|
||||
3. **Verify no open NCRs** (Non-Conformance Reports)
|
||||
4. **Get QC final approval**
|
||||
5. **Prepare handover package**
|
||||
|
||||
### Handover Documentation
|
||||
Package should include:
|
||||
- **Test packet summary**
|
||||
- **Complete weld list** with acceptance
|
||||
- **All NDT reports**
|
||||
- **Pressure test certificates**
|
||||
- **Material traceability**
|
||||
- **As-built drawings**
|
||||
|
||||
### System Handover
|
||||
Final steps:
|
||||
1. **Mark packet as "Ready for Handover"**
|
||||
2. **Get client approval** (if required)
|
||||
3. **Transfer to operations** team
|
||||
4. **Update system status** to "Handed Over"
|
||||
5. **Archive documentation**
|
||||
|
||||
## Common Tasks
|
||||
|
||||
### Daily Packet Review
|
||||
1. **Check progress** on active packets
|
||||
2. **Review NDT results** received
|
||||
3. **Update completion status**
|
||||
4. **Plan next day's activities**
|
||||
5. **Coordinate with inspection teams**
|
||||
|
||||
### Weekly Planning
|
||||
1. **Review upcoming deadlines**
|
||||
2. **Plan NDT scheduling** for next week
|
||||
3. **Check resource availability**
|
||||
4. **Update progress reports**
|
||||
5. **Coordinate with other departments**
|
||||
|
||||
### Monthly Reporting
|
||||
1. **Generate completion reports**
|
||||
2. **Analyze productivity trends**
|
||||
3. **Review quality metrics**
|
||||
4. **Plan resource adjustments**
|
||||
5. **Update project schedules**
|
||||
|
||||
## Working with Teams
|
||||
|
||||
### NDT Coordinators
|
||||
- **Submit requests** early for better scheduling
|
||||
- **Provide clear access** requirements
|
||||
- **Communicate urgency** levels clearly
|
||||
- **Follow up** on pending results
|
||||
|
||||
### Construction Teams
|
||||
- **Coordinate completion** schedules
|
||||
- **Communicate test requirements** early
|
||||
- **Plan access** for inspections
|
||||
- **Report completion** promptly
|
||||
|
||||
### QC Department
|
||||
- **Review documentation** thoroughly
|
||||
- **Escalate issues** quickly
|
||||
- **Maintain standards** consistently
|
||||
- **Support resolution** efforts
|
||||
|
||||
## Troubleshooting
|
||||
|
||||
### Common Issues
|
||||
|
||||
**Packet won't close:**
|
||||
- Check for incomplete NDT
|
||||
- Verify all documentation uploaded
|
||||
- Look for open NCRs
|
||||
- Confirm all approvals received
|
||||
|
||||
**Can't add welds to packet:**
|
||||
- Check weld completion status
|
||||
- Verify no conflicts with other packets
|
||||
- Ensure weld meets packet criteria
|
||||
- Contact admin if system error
|
||||
|
||||
**Missing NDT reports:**
|
||||
- Check with inspection company
|
||||
- Verify report upload location
|
||||
- Look in other related packets
|
||||
- Contact NDT coordinator
|
||||
|
||||
### Quick Solutions
|
||||
- **Use search function** to find missing items
|
||||
- **Check filter settings** if data missing
|
||||
- **Refresh page** for latest updates
|
||||
- **Contact supervisor** for process issues
|
||||
|
||||
## Best Practices
|
||||
|
||||
### Planning
|
||||
- ✅ Start packets early in construction phase
|
||||
- ✅ Group logically by system/area
|
||||
- ✅ Plan NDT scheduling in advance
|
||||
- ✅ Coordinate with all stakeholders
|
||||
|
||||
### Execution
|
||||
- ✅ Update status promptly
|
||||
- ✅ Upload documents immediately
|
||||
- ✅ Communicate issues quickly
|
||||
- ✅ Follow established procedures
|
||||
|
||||
### Quality
|
||||
- ✅ Review all documentation thoroughly
|
||||
- ✅ Maintain complete traceability
|
||||
- ✅ Follow approval processes
|
||||
- ✅ Keep detailed records
|
||||
|
||||
## Getting Help
|
||||
|
||||
**For Process Questions:**
|
||||
- Review project procedures
|
||||
- Consult QC supervisor
|
||||
- Check industry standards
|
||||
- Ask experienced team members
|
||||
|
||||
**For System Issues:**
|
||||
- Try refresh/restart first
|
||||
- Note specific error messages
|
||||
- Contact IT support
|
||||
- Provide packet numbers for reference
|
||||
|
||||
Remember: Test Packets are your roadmap to successful system completion. Good organization here makes handover smooth and trouble-free!
|
||||