# Spool Area Release - Quick Guide / Hızlı Kılavuz ## 🔄 How System Calculates Spool Status / Sistem Spool Durumunu Nasıl Hesaplar ### English - The Algorithm **Step 1: Priority Numbers** ``` Waiting = Priority 1 (lowest/earliest) Manufacturing = Priority 2 QC = Priority 3 Paint = Priority 4 Completed = Priority 5 (highest/latest) ``` **Step 2: Find Lowest Status** - System looks at ALL shop welds (S type) in your spool - Takes the **LOWEST priority number** - Shows that status **Example:** ``` Spool SPL-001 has 10 welds: - 9 welds = "Completed" (priority 5) - 1 weld = "QC" (priority 3) Result: System shows "QC" ← because 3 is lower than 5 ``` **Step 3: Check Date Consistency** System compares dates for these checkpoints: - ✅ NDT Release Date - ✅ Clearance Date - ✅ Register Date - ✅ Paint Release Date - ✅ Spool NDT Check Date If dates don't match across all welds → adds ⚠️ warning **Example:** ``` Spool SPL-002 dates: - Weld 1: NDT Release = March 1 - Weld 2: NDT Release = March 1 - Weld 3: NDT Release = March 15 ← Different! Result: Shows ⚠️ warning icon ``` **Step 4: Show Signatures** System shows who approved what: - **Spool NDT Check** → NDT inspector who checked the spool - **Spool Paint Check** → Paint inspector who checked the spool - **NDT Release Check** → Person who released from NDT - **Paint Release Check** → Person who released from Paint When someone signs → Shows ✒️ + their name ### Türkçe - Algoritma **Adım 1: Öncelik Numaraları** ``` Waiting (Bekliyor) = Öncelik 1 (en düşük/erken) Manufacturing (Üretim) = Öncelik 2 QC (Kalite Kontrol) = Öncelik 3 Paint (Boya) = Öncelik 4 Completed (Tamamlandı) = Öncelik 5 (en yüksek/son) ``` **Adım 2: En Düşük Durumu Bul** - Sistem spool'daki TÜM atölye kaynaklarına (S tipi) bakar - **EN DÜŞÜK öncelik numarasını** alır - O durumu gösterir **Örnek:** ``` SPL-001 spool'unda 10 kaynak var: - 9 kaynak = "Tamamlandı" (öncelik 5) - 1 kaynak = "Kalite Kontrol" (öncelik 3) Sonuç: Sistem "Kalite Kontrol" gösterir ← çünkü 3, 5'ten düşük ``` **Adım 3: Tarih Tutarlılığını Kontrol Et** Sistem bu kontrol noktalarının tarihlerini karşılaştırır: - ✅ NDT Serbest Bırakma Tarihi - ✅ Temizlik Tarihi - ✅ Kayıt Tarihi - ✅ Boya Serbest Bırakma Tarihi - ✅ Spool NDT Kontrol Tarihi Tüm kaynaklar arasında tarihler uyuşmuyorsa → ⚠️ uyarısı ekler **Örnek:** ``` SPL-002 tarihleri: - Kaynak 1: NDT Serbest Bırakma = 1 Mart - Kaynak 2: NDT Serbest Bırakma = 1 Mart - Kaynak 3: NDT Serbest Bırakma = 15 Mart ← Farklı! Sonuç: ⚠️ uyarı ikonu gösterir ``` **Adım 4: İmzaları Göster** Sistem neyi kimin onayladığını gösterir: - **Spool NDT Kontrolü** → Spool'u kontrol eden NDT müfettişi - **Spool Boya Kontrolü** → Spool'u kontrol eden boya müfettişi - **NDT Serbest Bırakma Kontrolü** → NDT'den serbest bırakan kişi - **Boya Serbest Bırakma Kontrolü** → Boyadan serbest bırakan kişi Biri imzaladığında → ✒️ + ismini gösterir --- ## 📈 Visual Flow / Görsel Akış ### English ``` ┌─────────────────────────────────────┐ │ Start: View Spool List │ └──────────────┬──────────────────────┘ │ ▼ ┌─────────────────────────────────────┐ │ STEP 1: Collect all welds (S type) │ │ Example: SPL-001 has 10 welds │ └──────────────┬──────────────────────┘ │ ▼ ┌─────────────────────────────────────┐ │ STEP 2: Find LOWEST status │ │ Waiting(1) < Manufacturing(2) < │ │ QC(3) < Paint(4) < Completed(5) │ └──────────────┬──────────────────────┘ │ ▼ ┌─────────────────────────────────────┐ │ STEP 3: Compare dates │ │ • NDT Release Date │ │ • Clearance Date │ │ • Register Date │ │ • Paint Release Date │ │ • Spool NDT Check Date │ │ │ │ Different? → Add ⚠️ │ └──────────────┬──────────────────────┘ │ ▼ ┌─────────────────────────────────────┐ │ STEP 4: Show signatures │ │ • NDT Inspector → ✒️ John │ │ • Paint Inspector → ✒️ Sarah │ └──────────────┬──────────────────────┘ │ ▼ ┌─────────────────────────────────────┐ │ Display: Status + Warnings + Signs │ │ SPL-001: QC ⚠️ ✒️John ✒️Sarah │ └─────────────────────────────────────┘ ``` ### Türkçe ``` ┌─────────────────────────────────────┐ │ Başlangıç: Spool Listesini Görüntüle│ └──────────────┬──────────────────────┘ │ ▼ ┌─────────────────────────────────────┐ │ ADIM 1: Tüm kaynakları topla (S tip)│ │ Örnek: SPL-001'de 10 kaynak var │ └──────────────┬──────────────────────┘ │ ▼ ┌─────────────────────────────────────┐ │ ADIM 2: EN DÜŞÜK durumu bul │ │ Bekliyor(1) < Üretim(2) < │ │ Kalite(3) < Boya(4) < Tamamlandı(5) │ └──────────────┬──────────────────────┘ │ ▼ ┌─────────────────────────────────────┐ │ ADIM 3: Tarihleri karşılaştır │ │ • NDT Serbest Bırakma Tarihi │ │ • Temizlik Tarihi │ │ • Kayıt Tarihi │ │ • Boya Serbest Bırakma Tarihi │ │ • Spool NDT Kontrol Tarihi │ │ │ │ Farklı mı? → ⚠️ ekle │ └──────────────┬──────────────────────┘ │ ▼ ┌─────────────────────────────────────┐ │ ADIM 4: İmzaları göster │ │ • NDT Müfettişi → ✒️ Ahmet │ │ • Boya Müfettişi → ✒️ Ayşe │ └──────────────┬──────────────────────┘ │ ▼ ┌─────────────────────────────────────┐ │ Göster: Durum + Uyarılar + İmzalar │ │ SPL-001: Kalite ⚠️ ✒️Ahmet ✒️Ayşe │ └─────────────────────────────────────┘ ``` --- ## 📊 Spool Status - What Does It Mean? / Spool Durumu - Ne Anlama Gelir? ### English | Status | What It Means | Can I Release? | |--------|---------------|----------------| | **Waiting** | Spool hasn't started yet | ❌ No - Not ready | | **Manufacturing** | Currently being made in the shop | ❌ No - Still in production | | **QC** | Quality control is checking it | ❌ No - Under inspection | | **Paint** | Being painted | ❌ No - Not finished | | **Completed** | Finished and ready to go | ✅ Yes - Ready for release | **Important:** If your spool has 10 welds and 9 are "Completed" but 1 is "QC", the system shows "QC" to keep you safe from releasing too early. ### Türkçe | Durum | Ne Anlama Gelir | Serbest Bırakabilir miyim? | |-------|-----------------|----------------------------| | **Waiting** | Spool henüz başlamadı | ❌ Hayır - Hazır değil | | **Manufacturing** | Atölyede yapılıyor | ❌ Hayır - Hala üretimde | | **QC** | Kalite kontrol inceliyor | ❌ Hayır - Denetim altında | | **Paint** | Boyanıyor | ❌ Hayır - Bitmedi | | **Completed** | Bitmiş ve gönderilmeye hazır | ✅ Evet - Serbest bırakmaya hazır | **Önemli:** Spool'unuzda 10 kaynak varsa ve 9'u "Tamamlandı" ancak 1'i "Kalite Kontrol"deyse, sistem sizi erken serbest bırakmaktan korumak için "Kalite Kontrol" gösterir. --- ## 🔍 Icons You'll See / Göreceğiniz İkonlar ### English | Icon | What It Means | What Should I Do? | |------|---------------|-------------------| | ✒️ | Someone signed/approved this | Good! This person checked it | | ⚠️ | Warning - dates don't match! | Check why dates are different | | (no icon) | Normal, no problems | Nothing special to do | ### Türkçe | İkon | Ne Anlama Gelir | Ne Yapmalıyım? | |------|-----------------|----------------| | ✒️ | Biri imzaladı/onayladı | Güzel! Bu kişi kontrol etti | | ⚠️ | Uyarı - tarihler uyuşmuyor! | Tarihlerin neden farklı olduğunu kontrol et | | (ikon yok) | Normal, sorun yok | Özel bir şey yapma | --- ## What is the Spool Area Release Module? **English:** This module helps you release spools (pipe pieces) from the workshop to the construction site. It tracks who checked what, when it's ready, and warns you if something is wrong. **Türkçe:** Bu modül, spool'ları (boru parçalarını) atölyeden şantiyeye serbest bırakmanıza yardımcı olur. Neyi kimin kontrol ettiğini, ne zaman hazır olduğunu takip eder ve bir sorun varsa sizi uyarır. --- ## 🚀 How to Access / Nasıl Erişilir **English:** Login → **Shop** menu → **Spool Area Release** **Türkçe:** Giriş Yap → **Shop** (Atölye) menüsü → **Spool Area Release** --- ## 🎯 Key Features / Ana Özellikler ### 1️⃣ Revision Number (Revizyon Numarası) **English:** Shows the latest drawing revision automatically. You always work with current info. **Türkçe:** En son çizim revizyonunu otomatik gösterir. Her zaman güncel bilgiyle çalışırsınız. --- ### 2️⃣ Signature System (✒️ İmza Sistemi) **English:** When someone checks or approves, their name shows with ✒️ icon. You see instantly who approved what. **Türkçe:** Biri kontrol edip onayladığında, ismi ✒️ ikonu ile gösterilir. Neyi kimin onayladığını anında görürsünüz. --- ### 3️⃣ Smart Status (Akıllı Durum) **English:** System shows the **lowest** status to protect you. If 1 weld is "QC" and 9 are "Completed", it shows "QC" = not ready yet! **Türkçe:** Sistem sizi korumak için **en düşük** durumu gösterir. 1 kaynak "Kalite Kontrol"de ve 9'u "Tamamlandı" ise, "Kalite Kontrol" gösterir = henüz hazır değil! --- ### 4️⃣ Warning System (⚠️ Uyarı Sistemi) **English:** - ⚠️ means dates don't match - Example: Some welds released March 1, others March 15 - Fix the wrong date! **Türkçe:** - ⚠️ tarihler uyuşmuyor demek - Örnek: Bazı kaynaklar 1 Mart, diğerleri 15 Mart tarihli - Yanlış tarihi düzelt! --- ### 5️⃣ Two Counters (İki Sayaç) **English:** - **Counter 1:** Shop welds (S, F/S types) - **Counter 2:** Field welds (F type) **Türkçe:** - **Sayaç 1:** Atölye kaynakları (S, F/S tipleri) - **Sayaç 2:** Saha kaynakları (F tipi) --- ## 📋 How to Use / Nasıl Kullanılır ### Two Views / İki Görünüm **English:** 1. **Summary View** (default) = See all spools grouped 2. **Detail View** = Filter by ISO or Spool number to see each weld **Türkçe:** 1. **Özet Görünümü** (varsayılan) = Tüm spool'ları gruplu gör 2. **Detay Görünümü** = ISO veya Spool numarasına göre filtrele, her kaynağı gör --- ### Quick Check Before Release / Serbest Bırakmadan Önce Hızlı Kontrol **English:** - ✅ Status = "Completed"? - ✅ No ⚠️ warning icons? - ✅ All ✒️ signatures present? - ✅ Revision number shown? If YES to all → Ready to release! **Türkçe:** - ✅ Durum = "Tamamlandı" mı? - ✅ ⚠️ uyarı ikonu yok mu? - ✅ Tüm ✒️ imzalar var mı? - ✅ Revizyon numarası gösteriliyor mu? Hepsine EVET ise → Serbest bırakmaya hazır! --- ## ⚠️ Common Problems / Yaygın Sorunlar ### English | Problem | What to Do | |---------|------------| | ⚠️ icon appears | Check dates - some joints have different dates. Fix the wrong ones. | | No ✒️ signature | Find who needs to sign and remind them. | | Status not "Completed" | One or more welds aren't finished yet. Go to Detail View to find which ones. | | Can't release | Check: Is it "Completed"? Any ⚠️? All ✒️ present? | | No revision number | Drawing not in system. Add it to Document Management first. | ### Türkçe | Sorun | Ne Yapmalı | |-------|------------| | ⚠️ ikonu çıktı | Tarihleri kontrol et - bazı kaynakların farklı tarihi var. Yanlış olanı düzelt. | | ✒️ imza yok | Kimin imzalaması gerektiğini bul ve hatırlat. | | Durum "Tamamlandı" değil | Bir veya daha fazla kaynak bitmedi. Hangisi bitmediğini bulmak için Detay Görünümüne git. | | Serbest bırakamıyorum | Kontrol et: "Tamamlandı" mı? ⚠️ var mı? Tüm ✒️ var mı? | | Revizyon numarası yok | Çizim sistemde yok. Önce Doküman Yönetimi'ne ekle. | --- ## 💡 Quick Tips / Hızlı İpuçları **English:** 1. Always look at icons first: ✒️ = good, ⚠️ = fix it! 2. "Completed" status = safe to release 3. Before releasing: Check 4 things (status, warnings, signatures, revision) 4. Use Summary View for quick check, Detail View for investigation **Türkçe:** 1. Her zaman önce ikonlara bak: ✒️ = iyi, ⚠️ = düzelt! 2. "Tamamlandı" durumu = serbest bırakabilirsin 3. Serbest bırakmadan önce: 4 şeyi kontrol et (durum, uyarılar, imzalar, revizyon) 4. Hızlı kontrol için Özet Görünümü, araştırma için Detay Görünümü kullan --- ## 📞 Need Help? / Yardım mı Lazım? **English:** Contact Shop Department **Türkçe:** Atölye Departmanı ile iletişime geç