Weld Logs Trigger Reference Guide

Overview

When you update fields in a Weld Log record, the system automatically runs specific background processes (triggers) based on what you changed. This guide shows you exactly which triggers will run for each field change.

Field-to-Trigger Mapping

Fields: test_package_no, iso_number

Triggers that will run:

  • Test Package Update
  • Test Pack Base Status Changer
  • NDE Calculation Updates
  • Support Statistics Calculation
  • Punch List Processing
  • Golden Joints Tracking

What gets updated:

  • Test package records and statistics
  • Test package status (Waiting/On Going/Completed)
  • ISO quantity calculations
  • Welding progress tracking
  • Support progress calculations
  • Punch list quantities (A/B/C categories)

Fields: spool_number, iso_number, type_of_joint

Triggers that will run:

  • Spool Status Changer

What gets updated:

  • Spool status across the system
  • Spool completion tracking
  • Related ISO spool references
  • Old and new spool status updates

Line Engineering Fields

Fields: line_number (triggers on ANY field change)

Triggers that will run:

  • Line Lists Update (runs on every change)
  • Line-to-WeldLog Synchronization

What gets updated:

  • Line list timestamps (for cron triggers)
  • Engineering data sync from Line Lists
  • Piping specifications and pressures
  • Design parameters
  • All weld logs with same line number

NDE Matrix Fields

Fields: type_of_welds, fluid_code, type_of_joint

Triggers that will run:

  • NDE Matrix Update
  • NDE Requirements Calculation
  • NDE Matrix to WeldLog Sync

What gets updated:

  • NDE matrix records
  • Joint type classifications
  • NDE testing requirements (RT, UT, MT, PT, PMI, HT, Ferrite)
  • Fluid-specific NDE rules
  • Operating temperature and pressure
  • Piping class and fluid group

Material Classification Fields

Fields: material_no_1, material_no_2

Triggers that will run:

  • Material Group Update

What gets updated:

  • Russian material group classifications
  • Material compatibility checks
  • Steel grade mapping (80% similarity threshold)
  • RU material group assignments

Test Request Date Fields

Fields: vt_request_date, ht_request_date, ut_request_date, mt_request_date, pmi_request_date, pt_request_date, rt_request_date, ferrite_request_date

Triggers that will run:

  • Request Number Generation
  • Test Laboratory Synchronization
  • Test Table Updates

What gets updated:

  • Auto-generated request numbers
  • Laboratory assignments
  • Test scheduling
  • Request tracking
  • Test table records (radiographic_tests, ultrasonic_tests, etc.)

Paint & Construction Fields

Fields: line_number, fluid_code, spool_number, no_of_the_joint_as_per_as_built_survey

Triggers that will run:

  • Paint Follow Up Update
  • Construction Paint Logs Sync

What gets updated:

  • Paint follow-up records (SHOP/FIELD)
  • Construction paint log entries
  • Paint system specifications
  • Coating schedules
  • Brand names, RAL codes, thickness values
  • Paint cycle information

Handover Fields

Fields: line_number, project, design_area, piping_type

Triggers that will run:

  • Handovers Sync

What gets updated:

  • Handover records
  • Project completion tracking
  • Area-specific handover status
  • Work type assignments
  • Location mappings

Always Running Processes

These processes run regardless of which field you change:

  • Repair Logs Update - Updates repair status and dates
  • NDE Project Name Sync - Syncs project names to NDE matrices
  • Line Lists Update - Updates line list timestamps for cron triggers

Quick Reference Table

Field Changed Test Package Spool Line NDE Material Request Paint Handover
test_package_no
iso_number
spool_number
line_number
type_of_welds
fluid_code
type_of_joint
material_no_1
material_no_2
vt_request_date
project
design_area
piping_type
no_of_the_joint_as_per_as_built_survey

Common Scenarios

Scenario 1: Changing Test Package

Fields: test_package_no = "TP-002"
Triggers: Test Package Update + Test Pack Base Status Changer + Line Lists Update
Processing Time: ~3-4 seconds

Scenario 2: Changing Spool Number

Fields: spool_number = "SP-123-A"
Triggers: Spool Status Changer + Line Lists Update + Paint Follow Up
Processing Time: ~2-3 seconds

Scenario 3: Changing Material

Fields: material_no_1 = "A106 Gr.B"
Triggers: Material Group Update + Line Lists Update
Processing Time: ~1-2 seconds
Fields: test_package_no = "TP-002" + iso_number = "ISO-456"
Triggers: Test Package + Spool Status Changer + Line Lists Update
Processing Time: ~4-5 seconds
Fields: line_number = "L-001" + fluid_code = "HW"
Triggers: Line Lists + NDE Matrix + Paint Follow Up + Handovers
Processing Time: ~5-6 seconds

Scenario 6: Changing NDE Fields

Fields: type_of_welds = "BW" + fluid_code = "HW"
Triggers: NDE Matrix Update + Line Lists Update
Processing Time: ~3-4 seconds

Performance Tips

  • Single Field Changes: Fastest processing, only relevant triggers run
  • Related Field Changes: Moderate processing, multiple related triggers may run
  • Cross-System Changes: Slower processing when changes affect multiple modules
  • Bulk Updates: Consider the cumulative effect of multiple field changes
  • Line Lists Update: Runs on every change to keep data fresh

Troubleshooting

If Expected Data Doesn't Update

  1. Check if the field you changed has an associated trigger
  2. Verify the field value actually changed from its previous value
  3. Look at system logs for trigger execution confirmation
  4. Check if Line Lists Update ran (it runs on every change)

If Processing Seems Slow

  1. Identify which fields you changed
  2. Count how many trigger categories are affected
  3. Multiple triggers running simultaneously is normal for related fields
  4. Line Lists Update runs on every change for data freshness

If Data Appears Inconsistent

  1. Ensure related fields are updated together (e.g., test_package_no + iso_number)
  2. Check that all required fields have values
  3. Verify the sequence of your changes
  4. Check if NDE Matrix sync completed properly

Common Issues

  • Material Group Not Updated: Check if steel grade similarity is above 80%
  • Paint Follow Up Missing: Ensure line has S-type joints for SHOP records
  • Test Package Status Wrong: Verify welding completion percentages
  • NDE Requirements Missing: Check if joint type and fluid code match matrix

This guide reflects the current optimized trigger system that runs necessary processes based on field changes, with Line Lists Update running on every change to maintain data freshness.